NPP Olkiluotto 3 EPR |
Construction of the new AREVA EPR 3+gen. nuclear power plant in Finnland | x | x | POYRY | 2007-2009 |
NPP Flamanville 3 EPR |
Construction of the new AREVA EPR 3+gen. nuclear power plant in France | x | x | POYRY | 2008-2010 |
NPP Taishan 1&2 EPR |
Construction of the new AREVA EPR 3+gen. nuclear power plant in China | x | POYRY | 2009-2010 | |
NPP Mochovce 3&4 |
Completion of NPP Mochovce, Unit 3&4 | x | EGPi | 2010 | |
TPP Pruneřov |
Reconstruction of power plant Prunerov in Czech Republic | x | EGPi | 2011 | |
Delta |
Rack station design |
x | DELTE Electronics | 2011 | |
NPP Mochovce 3&4 |
Seismic analysis of equipment consoles, completion of NPP Mochovce, Unit 3&4 |
x | x | ENEL/VUJE | 2011 |
NPP Mochovce 3&4 |
Seismic analysis of gamma spectrometer measuring device, completion of NPP Mochovce, Unit 3&4 |
x | x | ENEL/VUJE | 2011 |
NPP Metsamor |
Modernization of Metsamor power plant in Armenia | x | x | VUEZ | 2011 |
Autoservis Kolačín |
AUTOSERVIS B.R.P Top in Velky Kolacín in Slovakia - Architectural design and project documentation | x | x | BRPTop | 2011 |
Agro Šaľa |
Production of compound feed in Sala | x | x | AGM | 2011 |
NPP Mochovce 3&4 |
Stress and seismic analysis of pipe hangers and pipe supports, completion of NPP Mochovce, Unit 3&4 |
x | TECHNOS | 2011 | |
NPP Mochovce 3&4 |
Processing of proof documentation including stress and seismic calculation and optimization of pipe routing, completion of NPP Mochovce, Unit 3&4 |
x | TECHNOS | 2011 | |
NPP Mochovce 3&4 |
Processing of proof documentation in decontamination facility of NPP Mochovce, stress and seismic analysis & optimization, determining forces and anchor plate calculation |
x | TECHNOS | 2011 | |
NPP Mochovce 1&2 |
Project of changing of feedwater pipe for steam turbine in NPP Mochovce, Unit 1 | x | x | MODRANY | 2011 |
NPP Mochovce 1&2 |
Analysis of pipe resonance of accident feeding pipe system in NPP Mochovce, Unit 1&2 | x | MODRANY | 2011 | |
NPP Mochovce 3&4 |
Pipe stress and seismic analysis of Radiation control facility, completion of NPP Mochovce, Unit 3&4 |
x | x | EGPi | 2011 |
TPP Yunus Emre |
YUNUS EMRE 2x 145 MW CFPP |
x | EGPi | 2011 | |
CHP Duslo Sala |
Pipelines stress analysis, urea production, chemical plant Duslo Sala, Slovakia | x | x | DUSLO | 2011 |
NPP Mochovce 1&2 |
Exchange flow jets of flow measurement, feedwater pipeline of steam turbine in NPP Mochovce, Unit2 |
x | x | MODRANY | 2011 |
NPP Mochovce 3&4 |
Pipe stress analysis of HVAC drain system, complation of NPP Mochovce, Unit 3&4 |
x | TECHNOS | 2012 | |
NPP Jaslovske Bohunice |
System flow analysis in recirculation of active protection of the reactor, calculation of permissible flow and determination of throttling, NPP J.Bohunice Unit 2 | x | MODRANY | 2012 | |
NPP Mochovce 3&4 |
Processing of design specification of pipe system in radiation control facility, completion of NPP Mochovce, Unit 3&4 |
x | x | ENEL/VUJE | 2012 |
WWTP Humenné |
Independent stress analysis of wiping traverse platform of WWTP Humenne, Slovakia |
x | x | ALVEST | 2012 |
NPP Bohunice |
Project documentation of the emergency system for transportation to NPP Metsamor |
x | ENEL/VUJE | 2012 | |
NPP Mochovce 3&4 |
Stress and seismic analysis of LPDU bracket including verification protocols |
x | ENEL/VUJE | 2012 | |
WPP Gabčíkovo |
Design and calculation of lightweight construction of impeler inspection platform on hydroelectric power plant Gabcikovo VEG66028 | x | x | SKODA | 2012 |
SPP |
Computational simulations to identify the cause of resonance in transportation of natural gas pipelines | x | eustream | 2012 | |
TPP Eemshaven |
The design of piping, hangers and support, PDMS 3D model |
x | KIB, KUROTEC | 2012 | |
CHP Lenzing Tencel |
Lenzing - TENCEL | x | KIB | 2012 | |
NPP Mochovce 3&4 |
The design of piping, hangers and support of room 504, completion of NPP Mochovce, Unit 3&4 |
x | ENEL/VUJE | 2013 | |
NPP Mochovce 3&4 |
Advisory and consultancy services for HCC and SOR system, completion of NPP Mochovce, Unit 3&4 |
x | ENEL/VUJE | 2013 | |
NPP Mochovce 3&4 |
Project documentation of radiation protection system, completion of NPP Mochovce, Unit 3&4 |
x | x | ENEL/VUJE | 2013 |
WWTP SEINE AVAL |
SEINE AVAL |
x | GDF SUEZ | 2013 | |
NPP Mochovce 3&4 |
Developing a catalog of standardized anchoring and fastening the pipes up to DN 50, completion of NPP Mochovce, Unit 3&4 | x | x | ENEL/VUJE | 2013 |
NPP Mochovce 3&4 |
Develop a methodology for the design, construction and installation of pipes up to DN 50, completion of NPP Mochovce, Unit 3&4 | x | x | ENEL/VUJE | 2013 |
NPP Mochovce 3&4 |
Stress and seismic analysis of krypton monitor bracket, completion of NPP Mochovce, Unit 3&4 | x | x | ENEL/VUJE | 2013 |
NPP Mochovce 3&4 |
Stress and seismic analysis of GIM202, TVD-SAM201 a SGLM202 monitor brackets, completion of NPP Mochovce, Unit 3&4 | x | x | ENEL/VUJE | 2013 |
TPP Eemshaven |
TPP Eemshaven, The design of piping, hangers and support, PDMS 3D model, completion of TPP Eemshaven, Germany |
x | ETABO | 2013 |